Ninghai Pumped Storage Power Project
Ninghai Pumped Storage Power Project
Ninghai Pumped Storage Power Project
Introduction of TBM method to vertical shaft construction
Application of the concept of tunnel excavation to vertical shaft construction, realizing the mechanized, intelligent and factorial construction of large blind vertical shaft construction.
Project Background
The full-face excavation mechanical synchronous mucking system has higher efficiency and lower energy consumption compared with traditional mucking methods such as the slurry and vacuum ones, and has successfully solved the international problem of synchronous construction of excavation and mucking. The pioneer shaft remote control system, has improved the safety and comfort of shaft construction.
right side
Vertical section of the ventilation shaft at Ninghai Pumped Storage Power Station
The SBM has bored 4.82 m per day, much more efficient than the traditional method.
The SBM has completed 198 m deep tunnel and achieved breakthrough.
Project Information
| Tunnelling length: | 198m |
| Geology: | Tuff |
| Contractor: | Sinohydro Bureau 12 Co., Ltd. |
TBM Parameter
| TBM type: | Shaft Boring Machine (SBM) |
| TBM S/N: | CREC 599 |
| Boring Dia: | 7.83 m |
| Main drive power: | 1,500 KW |
| Best performance: | 4.82m per day |
Project Characteristics
| It faces the difficulty of upward muck discharge in blind shaft. |
| It’s the first application of TBM concept to vertical shaft construction in China. |
| Advanced technologies help to save labor cost while enhancing tunnelling efficiency. |