Transmission Cable Tunnel Project for YongIn Semiconductor Cluster Industrial Complex
Transmission Cable Tunnel Project for YongIn Semiconductor Cluster Industrial Complex
Transmission Cable Tunnel Project for YongIn Semiconductor Cluster Industrial Complex
Three TBMs serve infrastructure construction in Korea
A total of 3 sets of Φ 4.38 m CREG single shield TBMs have been employed to bore three sections of a 5,183 meter long transmission cable tunnel for Yongln Semiconductor Cluster Industrial Complex, and the TBMs are responsible for 1,112 m, 2,119 m and 1,952 m respectively. Based on reliable performance, the TBMs achieve tunnel breakthrough 7 months ahead of schedule, winning high praise and recognition from the client.
Project Background
The project is CREG's third TBM order in Korea and thus a full spectrum of CREG TBMs have been applied to the market besides the previous EPB TBM for Incheon Metro Line Geomdan Extension and the slurry TBM for Shincheongju Cable Tunnel. It is also a vivid demonstration of CREG's contribution to serving infrastructure construction of Korea.
right side
Transmission Cable Tunnel Route
The TBMs completed tunnel breakthrough 7 months ahead of schedule with reliable performance.
Project Information
| Tunnelling length: | 5,183 m |
| Geology: | Granite, gneiss, weathered rock |
| Contractor: | SK ecoplant Co., Ltd. |
TBM Parameter
| TBM type: | Single shield TBM |
| TBM S/N: | CREC 1141, CREC 1142, CREC 1143 |
| Boring Dia: | 4.38 m |
| Main drive power: | 1400 kw |
| FAT date: | TBM1: May.2023; TBM2: Jan.2023; TBM3: August.2023 |
| Best performance: | 261.6 m per month, 15.53m per day. |
Project Characteristics
| The tunnel passes through fracture zone and the Sangji River, which poses high requirement on the performance of the TBMs. |
| Robust structure enables the TBMs to cope with high abrasiveness of surrounding rock. |