Changsha Leifeng Water Plant Raw Water Pipeline Project
Pipe Jacking Shield Machine Solutions for Challenges in Super‑long Water Diversion Tunnel Construction
Given the super‑long distance and high abrasiveness of the project, the TBM features a specialized pipe jacking shield machine design. It initially employs a pipe jacking mode for single jacking, and once the jacking force reaches its limit, it switches to the TBM mode to maintains construction progress, effectively fulfilling the requirements of long‑distance tunneling tasks. During the actual construction process, the machine advanced 1,136m in pipe jacking mode before reaching its maximum jacking force. It then switched to the TBM mode to complete the remaining 451m, ultimately achieving a breakthrough for the entire project line.
Project Background
This project is a key livelihood initiative in Changsha City, primarily aimed at addressing the water supply challenges faced by districts on the west bank of the Xiangjiang River due to the city's westward expansion. It holds significant strategic importance for ensuring the safety and reliability of the water supply in this area. The pipe jacking shield machine employed in this construction section effectively addresses the specific requirements of non‑excavation, small diameter, long‑distance, and curved jacking for urban underground pipe network construction. In the future, it is anticipated to be extensively used in the construction of underground pipe networks for urban drainage, electricity, and gas, thereby significantly improving the mechanization of urban underground infrastructure projects.
Changsha Leifeng water plant raw water pipeline project route
The pipe jacking shield machine meets municipal pipe gallery excavation.
Pipe jacking shield machine "CREG 1268" rolled off the production line.
Project Information
| Project type: | municipal water diversion tunnel |
| Tunneling length: | 1,587m |
| Geology: | moderately weathered quartz sandstone, moderately weathered fine sandstone, with maximum rock strength of 164MPa; |
| Contractor: | Anhui Yuanzu Construction Co., Ltd. |
Parameters
| Machine type: | pipe jacking shield machine |
| Machine S/N: | CREC 1268 |
| Cutterhead diameter: | Φ3,680mm |
| Main drive power: | 360 kW |
| Launch time: | February 2023 |
| Best performance: | 19.2m per day |
Project Characteristics
| The machine advanced a total of 1,587m in total; |
| The maximum rock strength is 164MPa; |
| The site features abundant groundwater and is connected to underground rivers. |